Girod Street Improvements | Engineering Projects
Here Meyer Engineers, Ltd. undertook a project focused on improvements along Girod Street from Lakeshore Drive to Monroe Street. The work performed included construction of concrete sidewalks on both sides, closing in all ditches, a two-inch asphalt overlay, installation of decorative street lights, striping, signage, new concrete parking areas, concrete curbs and landscaping.
Start Date: February 2000
Substantial Completion Date: January 2004
Construction Cost: $1,400,000
Substantial Completion Date: January 2004
Construction Cost: $1,400,000
“Meyer Engineers, Ltd. is a top notch Engineering, Construction Management firm that is always a vital member in the performance of a quality project. The Department of Works would recommend Meyer Engineers, Ltd. to any Owner requiring Engineering or Construction Management services.”